CCWD Update on Water Pipeline in West Point

   Per CCWD, the West Point USDA and Project 84 potable water pipeline replacement grant project is significatntly ahead of schedule due to the hard work of the contractor Mozingo Construction.

   The mainline pipe replacement project has been completed and Mozingo is in the process of installing the service connections.

   It is estimated that the service line work will be completed by September 28, 2012. Mozingo is planning on paving Main Street and Highway 26 starting on Saturday September 29, 2012.

   Mozingo has rearranged their schedule to insure there is no conflict with Lumber Jack Day events.

   Paving is expedted to be completed by October 5, 2012.